New silos for Lübeck

 

 

The cement plant Lübeck has appointed Intercem to supply a silo unit consisting of 4 steel silos with a capacity of 1,200 m3 each. In addition, the bulk loading and the complex cement conveying via air slides and bucket elevators leading over the complete area of the plant are part of the scope of supply. Further services:

Engineering and associated plant components, such as

support structure
catwalks
filters
bucket elevators
return lines
electrical equipment

as well as building application and dispatch automation.

Intercem was able to convince the German cement manufacturer of its efficiency and flexibility with this turn-key solution. Completion is scheduled for the third quarter of 2019.

 

Other highlights from the InterCem world

Highlights

DIN EN ISO 9001 – Certification obtained

We are proud that we received the certification for quality management according to DIN EN ISO 9001 on 15.10.2021. Certificate_0121091_9001_EN

Order received for a cement grinding plant with VRM from raw material truck receiving station to packing plant. Intercem will execute the entire engineering and supervision services as well as the deliveries for this project.

Second clinker and raw material receiving hopper InterHop completed

Maximum flexibility, fast truck loading and dust-free operation – all this is guaranteed by the InterHop clinker and raw material receiving hopper. […]

Activate your potential - Talk to us.