Rotary kiln capacity enhancement…

…for achieving an increase in clinker production from 800 to 2200 tonnes per day

Location: Sharjah Cement Factory, United Arab Emirates

Scope of service:

  • New raw material transport and new metering
  • New 5-stage heat exchanger with calciner
  • Reduction of kiln length from 159 m to 51 m
  • New installation of a tertiary air duct
  • New clinker cooler with dedusting filter
  • New clinker conveyor assemblies
  • New electrics and automation

Time taken: 16 months in total (incl. technical clarification)

Production stop: 10 weeks

Acting as a general contractor, Intercem supplied all the required engineering work, as well as all mechanical and electrical equipment on a turn-key basis. The project was completed successfully within the agreed timeframe. The customer was so satisfied with the results that it commissioned Intercem to supply a new raw mill, which was also planned, assembled and handed over on schedule – meeting all the customer’s expectations. (Oelde, September 2007)