DR CONGO: Mind the gap

Due to an enormous leak of hot raw meal between the pre-heat exchanger and the rotary kiln, an Intercem kiln inlet seal was successfully installed. Using the latest scanning technology, the actual conditions of the plant were recorded to serve as a basis for engineering work. Building on this, factors that would be relevant to the process were taken into account and the construction planning and assembly work carried out. The dismantling and assembly process took 2 weeks.