Intercem was awarded a contract for the construction of a cement grinding plant with a capacity of approximately 2.8 million tpa for West Africa in July 2022.

Project description

The contract includes

– 2 truck unloading stations 700 tph

– 1 raw material storage with a capacity of 35,000 t

– 1 clinker dome with a capacity of 100,000 tph

– 1 grinding plant with a VRM 390 tph

– 4 cement silos of 5,400 tph each

– 5 packing lines

– 10 truck loading stations

and corresponding truck scales, laboratory equipment, electrical equipment and automation as well as all related facilities.

The steel construction, the entire sheet metal fabrications, the subsystems, the complete engineering, the erection supervision and the commissioning are also included in the scope of supply and services. All equipment is supplied exclusively by well-known European manufacturers.

Other highlights from the InterCem world

Highlights

DIN EN ISO 9001 – Certification obtained

We are proud that we received the certification for quality management according to DIN EN ISO 9001 on 15.10.2021. Certificate_0121091_9001_EN

Order received for a cement grinding plant with VRM from raw material truck receiving station to packing plant. Intercem will execute the entire engineering and supervision services as well as the deliveries for this project.

Second clinker and raw material receiving hopper InterHop completed

Maximum flexibility, fast truck loading and dust-free operation – all this is guaranteed by the InterHop clinker and raw material receiving hopper. […]

Activate your potential - Talk to us.