After the contract between KCCL and Intercem was signed in September 2014, Intercem has supplied a 90 tph cement grinding plant with a ball mill, a clinker storage and four  1000 t steel cement silos. Except the foundation works all further deliveries and services were included in Intercem’s scope of supply. Moreover, the 8-spout-packing line – ordered directly from the manufacturer by the customer – was completed, installed and commissioned by Intercem. Raw material is stored in a new raw material storage. Furthermore 3 separate vibration feeders, 2 belt conveyors and a bucket elevator were installed. The 4 silos dispose of truck loading stations and the finished product is transported via air conveyor troughs from the silos to the new packing line.

At the end of 2015, an additional contract was placed by KCCL. Due to the fact that the humidity content of the raw material Pozzolan appeared much higher than initially expected and specified. For this reason it was decided to order a Pozzolan-Dryer as well as a further storage for primary crushing and drying of the raw material at Intercem. Construction and installation of these additional assets have meanwhile been finished and the plant including the Pozzolan-Dryer – with a throughput of 40 tph – was commissioned. So a further semi-turnkey order could be successfully completed – as usual according to Intercem’s motto: “Fast, fair, flexible”

E-Mail sendenSo finden Sie uns+49 2522 92058-0